(19-11-2021, 10:27 AM)debono Wrote: For reclaimed land, the main contractor needs to work the earth, to install "vertical drains" to remove ground water, it needs a few years to allow the ground to settle before any piling is carried out, else the concrete piles will simply sink into the earth, as reclaimed land is made up of marine clay......